Planned PRP production order calculation dates.
Hi All,
Had a question On Baan IV c4, Planned PRP production order calculation dates.
Scenario
1) Use Operation overlap in the customised routing.
2) Set the field "Plan Capacity Requirements for PRP Orders" = Yes in tipcs5201m000.
3) The Planned finish dates in tipcs5110m000(Maintain Planned PRP Production Orders) does not take into consideration the operation overlap used in the routing.
4) backward planning (PRP) does not consider overlapping % while forward planning (capacity planning or SFC planning) does.
Any particular reason as to why it is designed this way or is it a bug?
__________________
Kinley
|